The estimated total cost for constructing a 100 sq. yds. ground-floor house ranges from ₹18 lakhs to ₹35 lakhs This comprehensive guide outlines the phase-wise breakdown, material expenses, labour costs, and additional factors to consider.
Phase-Wise Breakdown Construction Costs for House
1. Design and Planning (5%): ₹0.9-1.75 lakhs
– This initial stage involves hiring architects, engineers, and designers to create a customised blueprint for your dream home.
2. Site Preparation (10%): ₹1.8-3.5 lakhs
– Site preparation encompasses clearing the land, excavating, and levelling the ground to ensure a stable foundation.
3. Foundation and Structure (40%): ₹7.2-14.2 lakhs
– Constructing the foundation and structure is crucial, involving laying the groundwork, building columns, and installing roofing.
4. Utility Installation (15%): ₹2.7-5.3 lakhs
– Installing essential utilities such as plumbing, electrical systems, and HVAC ensures a functional and comfortable living space.
5. Finishing Touches (30%): ₹5.4-10.5 lakhs
– The final stage involves adding finishes like flooring, painting, and fixtures to make your house a home.
Material Expenses for Construction Costs for House
1. Cement: ₹0.75-1.5 lakhs
2. Steel: ₹1.2-2.4 lakhs
3. Bricks: ₹0.6-1.2 lakhs
4. Sand: ₹0.3-0.6 lakhs
5. Aggregate: ₹0.3-0.6 lakhs
6. Woodwork: ₹1.2-2.4 lakhs
7. Electrical: ₹0.6-1.2 lakhs
8. Plumbing: ₹0.3-0.6 lakhs
9. Flooring: ₹0.6-1.2 lakhs
10. Painting: ₹0.3-0.6 lakhs

Labour Costs Construction Costs for House
1. Masonry: ₹1.2-2.4 lakhs
2. Carpentry: ₹0.6-1.2 lakhs
3. Electrical: ₹0.3-0.6 lakhs
4. Plumbing: ₹0.3-0.6 lakhs
5. Painting: ₹0.3-0.6 lakhs
Additional Factors to Consider Construction Costs for House
1. Location (urban/rural): Urban areas typically have higher construction costs due to increased labour and material expenses.
2. Material quality (standard, high-end, luxury): Choosing premium materials significantly impacts overall costs.
3. Labour rates (skilled/unskilled): Hiring skilled labour increases costs but ensures better quality.
4. Design complexity (simple, moderate, complex): Intricate designs require more materials and labour, raising costs.
5. Local regulations and taxes: Compliance with local building codes and taxes adds to the overall expense.
Timeline
1. Planning and design: 1-3 months
2. Site preparation: 1-2 months
3. Foundation and structural work: 3-6 months